Fri Aug 21 16:37:22 2009, Christian Irmler, BELLE, internal calibration 40 MHz hit mode, cal006, , 21.08.2009 16:30:33,
|
Belle DUT, intcal
HV=80V, 40 MHz, no beam
hit mode
switched back to internal 40 MHz clock |
Fri Aug 21 17:14:58 2009, Wolfgang Kiesenhofer, , S/N Histograms Raw (no data selection), run001 (strips), run002 (pitch adapter), run003 (upper edge), , ,
|
|
Fri Aug 21 22:42:32 2009, Thomas Bergauer, common, EUDAQ config file used when running with telescope, , , ,
|
Used until Friday, 21.08.09:
AndMask = 0xf # 4x4 mm scintillator for trigger
Used since Friday, 21.08.09:
AndMask = 0xc # 9x9 mm scintillator for trigger
Local trigger using TLU only: ALWAYS WITH 9x9mm scintillator
|
Sat Aug 22 11:54:49 2009, Thomas Bergauer, common, beam profile, , , ,
|
beam shifted a bit in vertical direction downwards since 21. August 09 evening
Beam configuration:
Beam configuration file: H6b.802 (FM HAD (P0 off, H8=+180) PARLALLEL IN H6B SILC 2008 |
Sat Aug 22 13:28:53 2009, Wolfgang Kiesenhofer, Pt_ITE512, runlist for pt-module angle-scan, , , ,
|
Preliminary run list for pt-modules + ite512 + silc1, silc2, silc5, silc6
run |
angle[deg] |
pos |
height (xy-table) |
importance |
events |
1 |
1 |
center module |
|
+ |
10k |
2 |
2 |
center module |
|
+ |
10k |
3 |
3 |
center module |
|
+ |
10k |
4 |
4 |
center module |
|
+ |
10k |
5 |
5 |
center module |
|
+ |
10k |
6 |
6 |
center module |
|
+ |
10k |
7 |
7 |
center module |
|
+ |
10k |
8 |
8 |
center module |
|
+ |
10k |
9 |
9 |
center module |
|
+ |
10k |
10 |
10 |
center module |
|
+ |
10k |
11 |
12 |
center module |
|
+ |
10k |
12 |
14 |
center module |
|
- |
10k |
13 |
16 |
center module |
|
- |
10k |
14 |
0 |
center module |
|
+ |
? depends on ite512 |
15 |
0 |
upper pos |
|
+ |
10k |
16 |
0 |
lower pos |
|
+ |
10k |
|
Sat Aug 22 15:12:44 2009, Thomas Bergauer, common, beam profile, , , ,
|
playing with TRIM4 in vertical plane (setting to 20A current) shifted beamspot back to center position
Beam configuration:
Beam configuration file: H6b.802 (FM HAD (P0 off, H8=+180) PARLALLEL IN H6B SILC 2008
Rate: 3.35E5 particles/spill (measured with SCINT8 in beamline)
Particle Production Applet
Calculator applet
For +120 Gev/c beam:
Pi+ |
55.67 % |
p |
38.95 % |
K+ |
5.38 % |
|
Sat Aug 22 22:14:50 2009, Christian Irmler, BELLE, internal calibration 40 MHz transparent mode + cooling, cal010, , 22.08.2009 22:24:22,
|
Belle DUT, intcal
HV=80V, 40 MHz, beam off
1 sample, transparent mode
external clock
cooling
chiller set to 13 deg.
Bypass removed to achieve better watter flow at the module!
Chiller pump is set to 2800 rpm |
Sun Aug 23 13:15:42 2009, Marko Dragicevic, Pt_ITE512, Current and Humindity during first Run, , , ,
|
Current of Pt modules during first run
Data of the run was dicarded.
Compressed air flow was at ~2 bars during run. Graph shows RH rise after switching of CA flow. Restarted at around 7% with very low pressure.
Timescales for RH and I graph are different!!!
after 3 hours first bottle of compressed air (dewpoint -170 degree C) is gone and sensor Pt-h01 starts to fluctuate again
Current of ITE512 plus 2 SiLC08 modules
HV=70V, Current: 25uA first, 29uA then, 35uA latest. now stable
|
Sun Aug 23 14:03:14 2009, Manfred Valentan, Pt_ITE512, Pt & ITE512 center position, 1 deg, run024, 20000, 23.08.2009 13:59:06,
|
Pt: 1 Grad, HV=200V, 0% RH
ITE512: HV=70V
X-Y-Table: x=99.6, y=36
Telescope: run7316 |
Sun Aug 23 17:18:25 2009, Christian Irmler, Pt_ITE512, pedestal correction, pedcorr008, , 23.08.2009 17:17:36 ,
|
Pt: 1 Grad, HV=200V, 0% RH, intcal, beam off
ITE512: HV=70V,
X-Y-Table: x=99.6, y=36 |
Sun Aug 23 23:38:27 2009, Georg Auzinger, , Phone numbers, , , ,
|
Georg #70
Wolfgang - Building: 41, Room: 204, Tel: ?
Manfred: Building 38, Room 522, Tel: 70522
Chrisu: B39, room 309, Tel: 79309
Bergi: Tel Zimmer: 79112, Handy: 16-2471
Maks: Tel Zimmer: 79117 |
Tue Aug 25 09:00:51 2009, Thomas Bergauer, , beam conditions, , , ,
|
manually changed TRIM3, TRIM4 and TRIM6 |
Wed Aug 26 14:26:13 2009, Wolfgang Kiesenhofer, ITE128, S/N final Single-Metal, run001 & run002, , ,
|
Most probable S/N, Single Metal Layer, 2D histogram fitted with langau in 5 bin (strips) slices. |
Wed Sep 2 14:15:17 2009, Wolfgang Kiesenhofer, ITE128, ITE 128 Cross-Talk, run002, , ,
|
Preliminary strip correlation (Kendalls Tau) for threshold = 3*stripnoise. |
Fri Dec 4 12:21:56 2009, Wolfgang Kiesenhofer, , ITE128 strip correlation kendall tau (preliminary result), , , ,
|
Kendall tau (rank correlation) for module 1 (single layer 1 / h13), module 2 (single layer 2 / h14), module 6 (standard sensor 2 / h12)
|
Fri Aug 21 12:22:43 2009, Christian Irmler, BELLE, APVDAQ standalone 31.8 MHz hit mode, run010, 75000, 21.08.2009 12:53:02, 21.08.2009 13:35:01
|
4 Belle DUTs
HV=80V, 31.8 MHz, 6 sample, 120 GeV
switched to external clock source
processed mode, hit cut = 4
beam position: p-side: APV2 of Origami, n-side: between APV1 and 2 of Origami (center of sensors)
JP-module is hit at APV3, module seems to be on a higher position than in past beam test (eventuelly flipped) |
Wed Aug 19 20:43:14 2009, Christian Irmler, ITE128, ITE128 shooting into strips w/o pitch adapter, low position, run001, 100600, 19.08.2009 20:42:08, 19.08.2009 22:54:21
|
DUT: SiLC 08_1, 6 x ITE128, SiLC 08_2
HV = 70V, 40MHz, 120 GeV
TLU trigger, w/o telescope
9x9 mm beam spot
height (y) = 154.0979
ITE128 shooting into strips w/o pitch adapter, low position |
Wed Aug 19 22:56:07 2009, Christian Irmler, ITE128, ITE128 shooting into strips w pitch adapter, upper position, run002, 100600, 19.08.2009 22:54:23, 20.08.2009 00:11:31
|
DUT: SiLC 08_1, 6 x ITE128, SiLC 08_2
HV = 70V, 40MHz, 120 GeV
TLU trigger, w/o telescope
9x9 mm beam spot
height (y) = 144.3099
ITE128 shooting into strips w pitch adapter, upper position |
Thu Aug 20 00:16:45 2009, Christian Irmler, ITE128, pedestal correction, pedcorr001, , 20.08.2009 00:14:21, 20.08.2009 00:24:28
|
DUT: SiLC 08_1, 6 x ITE128, SiLC 08_2
HV = 70V, 40MHz
pedestal correction
beam on
|
Thu Aug 20 10:48:39 2009, Christian Irmler, alignment_beam, internal calibration, cal002, , 20.08.2009 10:49:07, 20.08.2009 10:59:43
|
2 alignement modules
location in beam direction: h04-h03
HV=70V, 40MHz, 1 sample
no beam
module 1 (h03) is used w inverter off and higher base line |
|