  HEPHY logbook for testbeam at SPS June 2009  Not logged in ELOG logo
Message ID: 75     Entry time: Sat Aug 22 22:14:50 2009
Author: Christian Irmler 
Project: BELLE 
Subject: internal calibration 40 MHz transparent mode + cooling 
Run Number: cal010 
Events:  
StartTime: 22.08.2009 22:24:22 
EndTime:  

Belle DUT, intcal
HV=80V, 40 MHz, beam off
1 sample, transparent mode
external clock
cooling
chiller set to 13 deg.

Bypass removed to achieve better watter flow at the module!
Chiller pump is set to 2800 rpm