Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-rd50-desy-Oct2024 testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS June 2009  Not logged in ELOG logo
Message ID: 23     Entry time: Thu Aug 20 10:48:39 2009
Author: Christian Irmler 
Project: alignment_beam 
Subject: internal calibration 
Run Number: cal002 
Events:  
StartTime: 20.08.2009 10:49:07 
EndTime: 20.08.2009 10:59:43 

2 alignement modules

location in beam direction: h04-h03

HV=70V, 40MHz, 1 sample
no beam

module 1 (h03) is used w inverter off and higher base line

ELOG V3.1.5-fc6679b