IDdown Date Author Project Subject Run Number Events StartTime EndTime Text Attachments
  28   Thu Aug 20 12:35:13 2009 Christian Irmleralignment_beamtop right on sensor, point 3run68651060020.08.2009 12:31:3520.08.2009 12:48:042 alignement modules
location in beam direction: h04-h03
beam in center of sensor
  
  27   Thu Aug 20 12:18:40 2009 Christian Irmleralignment_beamtop left on sensor, point 2run6863 (telescope 6864)1060020.08.2009 12:07:2820.08.2009 12:25:572 alignement modules
location in beam direction: h04-h03
beam in center of sensor
  
  26   Thu Aug 20 11:38:11 2009 Christian Irmleralignment_beamtop center, point 7run6861 (+6862)1060020.08.2009 11:36:3520.08.2009 11:53:512 alignement modules
location in beam direction: h04-h03
beam in center of sensor
  
  25   Thu Aug 20 11:23:04 2009 Christian Irmleralignment_beambeam in center of sensor w telescoperun004 (6860 telescope)1060020.08.2009 11:09:50 20.08.2009 11:25:162 alignement modules
location in beam direction: h04-h03
beam in center of sensor
  
  24   Thu Aug 20 11:05:26 2009 Christian Irmleralignment_beampedeatal correctionpedcorr002 20.08.2009 11:05:4120.08.2009 11:09:352 alignement modules
location in beam direction: h04-h03
HV=70V, 40MHz, 1 sample
  
  23   Thu Aug 20 10:48:39 2009 Christian Irmleralignment_beaminternal calibrationcal002 20.08.2009 10:49:0720.08.2009 10:59:432 alignement modules
location in beam direction: h04-h03
HV=70V, 40MHz, 1 sample
  
  22   Thu Aug 20 00:31:45 2009 Christian IrmlerITE128ITE128 shooting into strips w pitch adapter, upper positionrun00310060020.08.2009 00:27:36 DUT: SiLC 08_1, 6 x ITE128, SiLC 08_2
HV = 70V, 40MHz, 120 GeV
TLU trigger, w/o telescope
  
  21   Thu Aug 20 00:16:45 2009 Christian IrmlerITE128pedestal correctionpedcorr001 20.08.2009 00:14:2120.08.2009 00:24:28DUT: SiLC 08_1, 6 x ITE128, SiLC 08_2
HV = 70V, 40MHz
pedestal correction
  
  20   Wed Aug 19 22:57:13 2009 Marko Dragicevic How-To    TLU (run from DAQPCHEPHY):
ssh
eudet@eudetmac001.cern.ch
ssh tlupc
  
  19   Wed Aug 19 22:56:07 2009 Christian IrmlerITE128ITE128 shooting into strips w pitch adapter, upper positionrun00210060019.08.2009 22:54:2320.08.2009 00:11:31DUT: SiLC 08_1, 6 x ITE128, SiLC 08_2
HV = 70V, 40MHz, 120 GeV
TLU trigger, w/o telescope
  
  18   Wed Aug 19 20:43:14 2009 Christian IrmlerITE128ITE128 shooting into strips w/o pitch adapter, low positionrun00110060019.08.2009 20:42:0819.08.2009 22:54:21DUT: SiLC 08_1, 6 x ITE128, SiLC 08_2
HV = 70V, 40MHz, 120 GeV
TLU trigger, w/o telescope
  
  17   Wed Aug 19 15:41:17 2009 Wolfgang KiesenhoferSiLCangle scan templates    Linie am rechten Seitenrand (in der Vorschau
unten leider nicht gut zu sehen) sollte mit
dem rechten Rand der Basisplatte abschließen
 13x 
  16   Wed Aug 19 15:37:37 2009 Christian IrmlerITE128internal calibrationcal001 15:31:29 8 modules, HV=70V, 40MHz, 1 sample
no beam 
APV 4,5: inverter off, higher baseline
  
  15   Fri Aug 14 21:36:17 2009 Markus Friedl Config files    Status of config files as of Friday 14
August 2009 late evening
  
  14   Fri Aug 14 19:35:43 2009 Thomas BergauerPt_ITE512intcal    HV=100V except h05-ITE-512 and h06-ITE-512
(runaway, HV off)
h01-Pt: 10uA
  
  13   Fri Aug 14 16:45:25 2009 Stephan Hänsel Module - Setups     

    5mm Inbus-Schlüssel

   3mm Inbus Schlüssel
  
  
  12   Tue Aug 11 14:03:57 2009 Marko Dragicevic Sensor Designs    Screenshots
HEPHY
Gallery
GDS File Viewer
 
 6x 
  11   Fri Jul 31 19:23:26 2009 Thomas Bergauer Laser Spot size    10cm nach Kollimator: Durchmesser 1.45mm (FWHM)
20cm
nach Kollimator: Durchmesser 1,54mm (FWHM)
 laser_spot_overview.jpglaser_spot_10cm.jpglaser_spot_20cm.jpglaser_spot_30cm.jpg 
  10   Fri Jul 17 14:03:21 2009 Stephan Hänsel What to measure     Origami
 
Testbeam08 Module
  
  9   Thu Jul 9 10:29:58 2009 Stephan HänselSiLCMeasurements - Modules     Pt Modules:

- Sensoren sind Luftfeuhtigkeitsempfindlich
  