Message ID: 24     Entry time: Thu Aug 20 11:05:26 2009
Author: Christian Irmler 
Project: alignment_beam 
Subject: pedeatal correction 
Run Number: pedcorr002 
Events:  
StartTime: 20.08.2009 11:05:41 
EndTime: 20.08.2009 11:09:35 

2 alignement modules

location in beam direction: h04-h03

HV=70V, 40MHz, 1 sample

beam on

module 1 (h03) is used w inverter off and higher base line

ELOG V3.1.5-fc6679b