Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS September/October 2010, Page 4 of 8  Not logged in ELOG logo
Entry  Tue Oct 5 17:50:23 2010, Christian Irmler, ITE, cal, cal012, 83800, 05.10.2010 17:50:26, 05.10.2010 18:09:48  

6 x SILC + 2 x ITE
HV=100V
telescope position: 124/48

DUTs and SILC4/5 swapped
new module order (downstream): SILC0 - SILC3 - SILC1 - W7 - W9 - SILC2 - SILC4 -SILC5
SILC1 and SILC2 are horizontal

beam on

modules flushed with dry air (black tube)
rel. humidity: ~0% @ 26°C

Entry  Tue Oct 5 10:23:09 2010, Manfred Valentan, BELLE, run, run47, 30000, 05.10.2010 10:21:20, 05.10.2010  

angle scan Origami 1 and  Micron wedge 1
HV = 100V
chiller set to 14°C

angle: 0°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: +7.5 (rotary table)

telescope run: 20153

Entry  Tue Oct 5 10:20:30 2010, Manfred Valentan, BELLE, run, run46, 350000, 05.10.2010 01:00:00, 05.10.2010 10:16:07 

angle scan Origami 1 and  Micron wedge 1
HV = 100V
chiller set to 14°C

angle: 15°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: -7.5 (rotary table)

telescope run: 20152

Entry  Mon Oct 4 23:59:05 2010, Manfred Valentan, BELLE, run, run45, , 04.10.2010 ??:??:??, 05.10.2010 00:56:48 

angle scan Origami 1 and  Micron wedge 1
HV = 100V
chiller set to 14°C

angle: 45°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: -37.5 (rotary table)

telescope run: 20151

Entry  Mon Oct 4 23:12:16 2010, Manfred Valentan, BELLE, run, run44, 30000, 04.10.2010 23:?:?, 04.10.2010 23.57.23 

angle scan Origami 1 and  Micron wedge 1
HV = 100V
chiller set to 14°C

angle: 30°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: -22.5 (rotary table)

telescope run: 20150

Entry  Mon Oct 4 21:01:25 2010, Christian Irmler, BELLE, run, run43, 30000, 04.10.2010 20:59:48, 04.10.2010 23:04:24 

angle scan Origami 1 and  Micron wedge 1
HV = 100V
chiller set to 14°C

angle: 60°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: -52.5 (rotary table)

telescope run: 20149

Entry  Mon Oct 4 20:16:19 2010, Christian Irmler, BELLE, cal, cal011, 83800, 04.10.2010 20:15:00,  

angle scan Origami 1 and  Micron wedge 1
HV = 100V
chiller set to 14°C

HV connection of Origami 1 repaired

Entry  Mon Oct 4 16:29:36 2010, Christian Irmler, common, beam settings, , , ,  beamprofile_run042.gifbeamsettings_run042.jpg

beam settings optimized by beamline operator

wire champer display fixed

Entry  Mon Oct 4 16:15:48 2010, Christian Irmler, Pt, run, run042, 25600, 04.10.2010 16:12:52, 04.10.2010 16:35:18 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=28.1A h02=2.4A
HV=200V beam on
angle: 47 deg

repetition of run040, but now biased :-)

telescope run 20148

Entry  Mon Oct 4 15:39:34 2010, Christian Irmler, Pt, run, run041, 25600, 04.10.2010 15:46:22,  

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=26.0A h02=13.4A
HV=200V beam on
angle: 45 deg
position axis = 232.5

repetition of run039

telescope run20147

Entry  Mon Oct 4 14:15:22 2010, Manfred Valentan, Pt, run, run040 --> unusable --> no bias, 25600, 04.10.2010 14:?:?, 04.10.2010 14:32:14 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=26.0A h02=13.4A
HV=200V beam on
angle: 47 deg

telescope run 20146

bias voltage has been ramped down during run039 --> needs to be repeated.

Entry  Mon Oct 4 12:50:13 2010, Erik Huemer, Pt, run, run039 --> run out of air --> repeat, 25600, 04.10.2010 12:45:17, 04.10.2010 14:00:00 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=26.0A h02=13.4A
HV=200V beam on
angle: 45 deg

run out of dry air  --> h01 run into compliance --> HV turned off during run automatically  --> has to be repeated

telescope run 20145

Entry  Mon Oct 4 12:24:38 2010, Erik Huemer, Pt, run, run038, 25600, 04.10.2010 12:22:09, 04.10.2010 12:43:40 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=26.6A h02=13.1A
HV=200V beam on
angle: 43 deg

telescope run 20144

Entry  Mon Oct 4 11:43:05 2010, Christian Irmler, Pt, run, run037, 25600, 04.10.2010 11:40:15, 04.10.2010 12:15:03 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=25.4A h02=13.1A
HV=200V beam on
angle: 41 deg

telescope run 20143

Entry  Mon Oct 4 10:43:45 2010, Marko Dragicevic, Pt, run, run036, 25600, 04.10.2010 10:33:05, 04.10.2010 11:35:51 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=24.9A h02=12.5A
HV=200V beam on
angle: 39 deg

telescope run 20142

Entry  Mon Oct 4 09:31:25 2010, Manfred Valentan, Pt, run, run035, 25600, 04.10.2010 09:28:40,  

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=24.7A h02=11.8A
HV=200V beam on
angle: 35 deg

telescope run 20140

Entry  Mon Oct 4 00:08:55 2010, Manfred Valentan, Pt, run, run034, 187000, 04.10.2010 00:03:18, 04.10.2010 09:22:07 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=21.9A h02=7.5A
HV=200V beam on
angle: 37

telescope run 20139

Entry  Sun Oct 3 22:53:49 2010, Manfred Valentan, Pt, run, run033, 25600, 03.10.2010 22.47:38, 04.10.2010 00:02:37 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=22.9A h02=6.9A
HV=200V beam on
angle: 33

telescope run 20138

Entry  Sun Oct 3 21:49:19 2010, Erik Huemer, Pt, run, run032, 25600, 03.10.2010 21:44:30, 03.10.2010 22.40.07 

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=22.9A h02=6.9A
HV=200V beam on
angle: 31

telescope run 20136

Entry  Sun Oct 3 20:44:40 2010, Erik Huemer, Pt, run, run031, 25600, 03.10.2010 19:42:34,  

Pt modules, angle scan

h01-Pt and h02-Pt
currents: h01=20.5A h02=6.5A
HV=200V beam on
angle: 29

telescope run 20135

ELOG V3.1.5-fc6679b