ID |
Date |
Author |
Project |
Subject |
Run Number |
Events |
StartTime |
EndTime |
89
|
Wed Oct 6 10:15:26 2010 |
Marko Dragicevic | Micron Baby | XY Positions After Irradiation | | | | |
center position: 119/50/(7.5)
top left (direction jura, bottom right on sensor): 127/56.5/7.5
bottom right (direction saleve, top left on sensor): 111/43.5/7.5 |
88
|
Tue Oct 5 18:13:05 2010 |
Christian Irmler | ITE | run | run048 | 533125 | 05.10.2010 18:14:57 | 06.10.2010 09:27:44 |
6 x SILC + 2 x ITE
HV=100V
telescope position: 124/48
telescope run: 20154-20155
DUTs and SILC4/5 swapped
new module order (downstream): SILC0 - SILC3 - SILC1 - W7 - W9 - SILC2 - SILC4 -SILC5
SILC1 and SILC2 are horizontal
beam on
modules flushed with dry air (black tube)
rel. humidity: ~0% @ 26°C |
87
|
Tue Oct 5 17:50:23 2010 |
Christian Irmler | ITE | cal | cal012 | 83800 | 05.10.2010 17:50:26 | 05.10.2010 18:09:48 |
6 x SILC + 2 x ITE
HV=100V
telescope position: 124/48
DUTs and SILC4/5 swapped
new module order (downstream): SILC0 - SILC3 - SILC1 - W7 - W9 - SILC2 - SILC4 -SILC5
SILC1 and SILC2 are horizontal
beam on
modules flushed with dry air (black tube)
rel. humidity: ~0% @ 26°C |
86
|
Tue Oct 5 10:23:09 2010 |
Manfred Valentan | BELLE | run | run47 | 30000 | 05.10.2010 10:21:20 | 05.10.2010 |
angle scan Origami 1 and Micron wedge 1
HV = 100V
chiller set to 14°C
angle: 0°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: +7.5 (rotary table)
telescope run: 20153 |
85
|
Tue Oct 5 10:20:30 2010 |
Manfred Valentan | BELLE | run | run46 | 350000 | 05.10.2010 01:00:00 | 05.10.2010 10:16:07 |
angle scan Origami 1 and Micron wedge 1
HV = 100V
chiller set to 14°C
angle: 15°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: -7.5 (rotary table)
telescope run: 20152 |
84
|
Mon Oct 4 23:59:05 2010 |
Manfred Valentan | BELLE | run | run45 | | 04.10.2010 ??:??:?? | 05.10.2010 00:56:48 |
angle scan Origami 1 and Micron wedge 1
HV = 100V
chiller set to 14°C
angle: 45°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: -37.5 (rotary table)
telescope run: 20151 |
83
|
Mon Oct 4 23:12:16 2010 |
Manfred Valentan | BELLE | run | run44 | 30000 | 04.10.2010 23:?:? | 04.10.2010 23.57.23 |
angle scan Origami 1 and Micron wedge 1
HV = 100V
chiller set to 14°C
angle: 30°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: -22.5 (rotary table)
telescope run: 20150 |
82
|
Mon Oct 4 21:01:25 2010 |
Christian Irmler | BELLE | run | run43 | 30000 | 04.10.2010 20:59:48 | 04.10.2010 23:04:24 |
angle scan Origami 1 and Micron wedge 1
HV = 100V
chiller set to 14°C
angle: 60°
axis 1: 92.4 (horizontal)
axis 2: 35 (vertical)
axis 3: -52.5 (rotary table)
telescope run: 20149 |
81
|
Mon Oct 4 20:16:19 2010 |
Christian Irmler | BELLE | cal | cal011 | 83800 | 04.10.2010 20:15:00 | |
angle scan Origami 1 and Micron wedge 1
HV = 100V
chiller set to 14°C
HV connection of Origami 1 repaired |
80
|
Mon Oct 4 16:29:36 2010 |
Christian Irmler | common | beam settings | | | | |
beam settings optimized by beamline operator
wire champer display fixed |
79
|
Mon Oct 4 16:15:48 2010 |
Christian Irmler | Pt | run | run042 | 25600 | 04.10.2010 16:12:52 | 04.10.2010 16:35:18 |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=28.1A h02=2.4A
HV=200V beam on
angle: 47 deg
repetition of run040, but now biased :-)
telescope run 20148 |
78
|
Mon Oct 4 15:39:34 2010 |
Christian Irmler | Pt | run | run041 | 25600 | 04.10.2010 15:46:22 | |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=26.0A h02=13.4A
HV=200V beam on
angle: 45 deg
position axis = 232.5
repetition of run039
telescope run20147 |
77
|
Mon Oct 4 14:15:22 2010 |
Manfred Valentan | Pt | run | run040 --> unusable --> no bias | 25600 | 04.10.2010 14:?:? | 04.10.2010 14:32:14 |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=26.0A h02=13.4A
HV=200V beam on
angle: 47 deg
telescope run 20146
bias voltage has been ramped down during run039 --> needs to be repeated. |
76
|
Mon Oct 4 12:50:13 2010 |
Erik Huemer | Pt | run | run039 --> run out of air --> repeat | 25600 | 04.10.2010 12:45:17 | 04.10.2010 14:00:00 |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=26.0A h02=13.4A
HV=200V beam on
angle: 45 deg
run out of dry air --> h01 run into compliance --> HV turned off during run automatically --> has to be repeated
telescope run 20145 |
75
|
Mon Oct 4 12:24:38 2010 |
Erik Huemer | Pt | run | run038 | 25600 | 04.10.2010 12:22:09 | 04.10.2010 12:43:40 |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=26.6A h02=13.1A
HV=200V beam on
angle: 43 deg
telescope run 20144 |
74
|
Mon Oct 4 11:43:05 2010 |
Christian Irmler | Pt | run | run037 | 25600 | 04.10.2010 11:40:15 | 04.10.2010 12:15:03 |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=25.4A h02=13.1A
HV=200V beam on
angle: 41 deg
telescope run 20143 |
73
|
Mon Oct 4 10:43:45 2010 |
Marko Dragicevic | Pt | run | run036 | 25600 | 04.10.2010 10:33:05 | 04.10.2010 11:35:51 |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=24.9A h02=12.5A
HV=200V beam on
angle: 39 deg
telescope run 20142 |
72
|
Mon Oct 4 09:31:25 2010 |
Manfred Valentan | Pt | run | run035 | 25600 | 04.10.2010 09:28:40 | |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=24.7A h02=11.8A
HV=200V beam on
angle: 35 deg
telescope run 20140 |
71
|
Mon Oct 4 00:08:55 2010 |
Manfred Valentan | Pt | run | run034 | 187000 | 04.10.2010 00:03:18 | 04.10.2010 09:22:07 |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=21.9A h02=7.5A
HV=200V beam on
angle: 37
telescope run 20139 |
70
|
Sun Oct 3 22:53:49 2010 |
Manfred Valentan | Pt | run | run033 | 25600 | 03.10.2010 22.47:38 | 04.10.2010 00:02:37 |
Pt modules, angle scan
h01-Pt and h02-Pt
currents: h01=22.9A h02=6.9A
HV=200V beam on
angle: 33
telescope run 20138 |