Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-rd50-desy-Oct2024 testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS June 2008, Page 3 of 4  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Project Subjectdown Run Number Events StartTime EndTime Text Attachments
  62   Tue Jun 3 14:59:14 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** angle-scan ***run28341000003.06.2008 14:56:3203.06.2008 15:15:37SiLC beam test - CERN SPS June 2008
Angle scan,  HV=100V, alpha = 40 degrees
8 modules, 40MHz, 6 samples, hor position
 drehteller_rot_40.gif 
  63   Tue Jun 3 15:39:57 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** angle-scan ***run28351000003.06.2008 15:36:4703.06.2008 15:55:34SiLC beam test - CERN SPS June 2008
Angle scan,  HV=100V, alpha = 50 degrees
8 modules, 40MHz, 6 samples, hor position
 drehteller_rot_50.gif 
  64   Tue Jun 3 16:14:26 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** angle-scan ***run28361000003.06.2008 16:13:1803.06.2008 16:33:20SiLC beam test - CERN SPS June 2008
Angle scan,  HV=100V, alpha = 60 degrees
8 modules, 40MHz, 6 samples, hor position
 drehteller_rot_60.gif 
  65   Tue Jun 3 16:53:20 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** angle-scan ***run28372000003.06.2008 16:49:4003.06.2008 17:26:49SiLC beam test - CERN SPS June 2008
Angle scan,  HV=100V, alpha = 0 degrees
8 modules, 40MHz, 6 samples, hor position
 drehteller_rot_00.gifdrehteller_rot.cdr 
  36   Mon Jun 2 13:19:10 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27873000002.06.2008 13:15:0402.06.2008 14:27:57SiLC beam test - CERN SPS June 2008
HV scan,  HV=100V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  37   Mon Jun 2 14:32:40 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27881000002.06.2008 14:31:1502.06.2008 14:51:55SiLC beam test - CERN SPS June 2008
HV scan,  HV=10V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  38   Mon Jun 2 14:55:38 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27891000002.06.2008 14:54:3302.06.2008 15:19:12SiLC beam test - CERN SPS June 2008
HV scan,  HV=20V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  40   Mon Jun 2 15:21:53 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27901000002.06.2008 15:20:4402.06.2008 15:38:04SiLC beam test - CERN SPS June 2008
HV scan,  HV=30V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  41   Mon Jun 2 15:41:20 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27911000002.06.2008 15:40:2002.06.2008 15:58:16SiLC beam test - CERN SPS June 2008
HV scan,  HV=40V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  42   Mon Jun 2 16:01:10 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run2792453602.06.2008 16:00:0902.06.2008 16:19:42SiLC beam test - CERN SPS June 2008
HV scan,  HV=50V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  43   Mon Jun 2 21:37:10 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28211000002.06.2008 21:32:5702.06.2008 21:51:55SiLC beam test - CERN SPS June 2008
HV scan,  HV=50V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  44   Mon Jun 2 21:54:34 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28221000002.06.2008 21:53:3702.06.2008 22:10:53SiLC beam test - CERN SPS June 2008
HV scan,  HV=60V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  45   Mon Jun 2 22:13:17 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28231000002.06.2008 22:12:4402.06.2008 22:34:49SiLC beam test - CERN SPS June 2008
HV scan,  HV=70V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  46   Mon Jun 2 22:37:13 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28241000002.06.2008 22:36:3702.06.2008 22:53:15SiLC beam test - CERN SPS June 2008
HV scan,  HV=80V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  47   Mon Jun 2 22:55:49 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28251000002.06.2008 22:55:0302.06.2008 23:12:09SiLC beam test - CERN SPS June 2008
HV scan,  HV=90V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  48   Mon Jun 2 23:14:58 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28261000002.06.2008 23:14:1902.06.2008 23:31:29SiLC beam test - CERN SPS June 2008
HV scan,  HV=120V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  49   Mon Jun 2 23:34:29 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28271000002.06.2008 23:33:4002.06.2008 23:52:04SiLC beam test - CERN SPS June 2008
HV scan,  HV=150V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  50   Tue Jun 3 00:20:06 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28281000002.06.2008 23:55:0603.06.2008 00:18:56SiLC beam test - CERN SPS June 2008
HV scan,  HV=200V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  17   Sat May 31 17:32:35 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) run2717649031.05.2008 15:57:5831.05.2008 16:09:21SiLC beam test - CERN SPS June 2008
8 modules, HV=100V, 40MHz, 6 samples
trigger: 9 mm opening, TLUControl.exe -d
  
  16   Sat May 31 17:29:40 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup)run27162000031.05.2008 14:59:2631.05.2008 15:56:23SiLC beam test - CERN SPS June 2008
8 modules, HV=100V, 40MHz, 6 samples
trigger: 9 mm opening, TLUControl.exe -d
  
ELOG V3.1.5-fc6679b