Message ID: 17     Entry time: Sat May 31 17:32:35 2008
Author: Markus Friedl 
Project: SiLC 
Subject: APVDAQ + telescope (0-sup)  
Run Number: run2717 
Events: 6490 
StartTime: 31.05.2008 15:57:58 
EndTime: 31.05.2008 16:09:21 
SiLC beam test - CERN SPS June 2008
8 modules, HV=100V, 40MHz, 6 samples
trigger: 9 mm opening, TLUControl.exe -d 10 -a 12 (now for real)
telescope: zero supressed, new firmware

trigger is now correct (9 x 9 mm2 window)
horizontal position ("target") = 0.0mm