Message ID: 38     Entry time: Mon Jun 2 14:55:38 2008
Author: Markus Friedl 
Project: SiLC 
Subject: APVDAQ + telescope (0-sup) *** HV-scan *** 
Run Number: run2789 
Events: 10000 
StartTime: 02.06.2008 14:54:33 
EndTime: 02.06.2008 15:19:12 
SiLC beam test - CERN SPS June 2008
HV scan,  HV=20V
8 modules, modules rearranged, 40MHz, 6 samples, hor position centered
trigger: 9 mm opening, TLUControl.exe -d 10 -a 12
telescope: 0sup., new firmware


HV scan after re-arranging the modules: