Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-rd50-desy-Oct2024 testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS June 2008, Page 2 of 4  Not logged in ELOG logo
ID Date Author Project Subject Run Number Eventsdown StartTime EndTime Text Attachments
  26   Sun Jun 1 15:08:17 2008 Markus FriedlSiLCAPVDAQ only (0-sup)run000310000001.06.2008 15:05:5101.06.2008 15:33:58SiLC beam test - CERN SPS June 2008 - HIT
MODE
8 modules, HV=100V, 40MHz, 6 samples, hor
  
  30   Sun Jun 1 18:23:38 2008 Markus FriedlSiLCVery simple trackingrun2719100000  Very simple alignment (manual linear x direction
shifting only, no rotation, assuming equal
z spacing) and tracking.
 silc_verysimple_res_2REF4.pngsilc_verysimple_res_012REF4567.png 
  33   Sun Jun 1 23:23:16 2008 Markus FriedlSiLCAPVDAQ only (0-sup)run000410000001.06.2008 23:21:1201.06.2008 23:41:09SiLC beam test - CERN SPS June 2008 - HIT
MODE
8 modules, HV=100V, 40MHz, 6 samples, hor
  
  24   Sun Jun 1 14:58:53 2008 Markus FriedlSiLCAPVDAQ onlyped0021000001.06.2008 14:55:3101.06.2008 14:59:06SiLC beam test - CERN SPS June 2008 - PEDESTAL
8 modules, HV=100V, 40MHz, 6 samples, hor
stage :=-7.5 mm
  
  25   Sun Jun 1 15:02:51 2008 Markus FriedlSiLCAPVDAQ onlyped0031000001.06.2008 15:00:5401.06.2008 15:04:14SiLC beam test - CERN SPS June 2008 - PEDESTAL
with beam
8 modules, HV=100V, 40MHz, 6 samples, hor
  
  32   Sun Jun 1 23:20:10 2008 Markus FriedlSiLCAPVDAQ onlyped0041000001.06.2008 23:16:5201.06.2008 23:19:59SiLC beam test - CERN SPS June 2008 - PEDESTAL
with beam
8 modules, HV=100V, 40MHz, 6 samples, hor
  
  37   Mon Jun 2 14:32:40 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27881000002.06.2008 14:31:1502.06.2008 14:51:55SiLC beam test - CERN SPS June 2008
HV scan,  HV=10V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  38   Mon Jun 2 14:55:38 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27891000002.06.2008 14:54:3302.06.2008 15:19:12SiLC beam test - CERN SPS June 2008
HV scan,  HV=20V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  40   Mon Jun 2 15:21:53 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27901000002.06.2008 15:20:4402.06.2008 15:38:04SiLC beam test - CERN SPS June 2008
HV scan,  HV=30V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  41   Mon Jun 2 15:41:20 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run27911000002.06.2008 15:40:2002.06.2008 15:58:16SiLC beam test - CERN SPS June 2008
HV scan,  HV=40V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  43   Mon Jun 2 21:37:10 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28211000002.06.2008 21:32:5702.06.2008 21:51:55SiLC beam test - CERN SPS June 2008
HV scan,  HV=50V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  44   Mon Jun 2 21:54:34 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28221000002.06.2008 21:53:3702.06.2008 22:10:53SiLC beam test - CERN SPS June 2008
HV scan,  HV=60V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  45   Mon Jun 2 22:13:17 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28231000002.06.2008 22:12:4402.06.2008 22:34:49SiLC beam test - CERN SPS June 2008
HV scan,  HV=70V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  46   Mon Jun 2 22:37:13 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28241000002.06.2008 22:36:3702.06.2008 22:53:15SiLC beam test - CERN SPS June 2008
HV scan,  HV=80V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  47   Mon Jun 2 22:55:49 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28251000002.06.2008 22:55:0302.06.2008 23:12:09SiLC beam test - CERN SPS June 2008
HV scan,  HV=90V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  48   Mon Jun 2 23:14:58 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28261000002.06.2008 23:14:1902.06.2008 23:31:29SiLC beam test - CERN SPS June 2008
HV scan,  HV=120V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  49   Mon Jun 2 23:34:29 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28271000002.06.2008 23:33:4002.06.2008 23:52:04SiLC beam test - CERN SPS June 2008
HV scan,  HV=150V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  50   Tue Jun 3 00:20:06 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** HV-scan ***run28281000002.06.2008 23:55:0603.06.2008 00:18:56SiLC beam test - CERN SPS June 2008
HV scan,  HV=200V
8 modules, modules rearranged, 40MHz, 6 samples,
  
  56   Tue Jun 3 10:58:54 2008 Markus FriedlBELLEAPVDAQ onlyped0071000003.06.2008 10:53:0403.06.2008 10:58:47SiLC beam test - CERN SPS June 2008
4 Belle modules, 40MHz, HV=80V, 6 samples
beam on (lower intensity)
  
  58   Tue Jun 3 12:32:51 2008 Markus FriedlSiLCAPVDAQ + telescope (0-sup) *** angle-scan ***run28311000003.06.2008 12:31:4203.06.2008 13:19:36SiLC beam test - CERN SPS June 2008
Angle scan,  HV=100V, alpha = 10 degrees
8 modules, 40MHz, 6 samples, hor position
 drehteller_rot_10.gif 
ELOG V3.1.5-fc6679b