Message ID: 116     Entry time: Sun Nov 23 15:09:53 2014
Author: Markus Friedl 
Project: Belle SVD 
Subject: PedestalRun 
Run Number: 001 
Events: 10000 
StartTime:  
EndTime:  
Data: Good 

Initial pedestal run with SVD3 setup and WedgeOld, FW993, BW993 (reading out 4 chips on every p-side)