Message ID: 29     Entry time: Tue Oct 16 22:19:21 2012
Author: Christian Irmler 
Project: MicronOrigami_gross 
Subject: cal 
Run Number: cal007 
Events: 83800 
StartTime: 16.10.2012 20:25:17  
EndTime: 16.10.2012 21:12:01  
Data: Unknown 

Origami Stack 2: Origami #4, #3, Wedge new1, old
HV = +-50V, Ibias=12.3µA
Position: verticallbtween APV 1&2 of 6,  left side of sensor,
wide side of wedge sensors

calibration for run013

Temperatures @ 21:00:

T11: -32 degC
T12: -33 degC
T13: -16 degC (obviously wrong value)
T14: -35 degC
T15: -18 degC
T16: -17 degC
T17: -15 degC
T18: -15 degC