Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS October 2011  Not logged in ELOG logo
Message ID: 93     Entry time: Wed Mar 7 16:03:30 2012
Author: Christian Irmler 
Project: BELLE 
Subject: Origami Module #4 
Run Number: run113 
Events: 100k 
StartTime: 07.03.2012 16:07:34 
EndTime: 07.03.2012 16:30:48  
Data: Unknown 

Sr90, small (new) scintillator, new trigger unit
Origami Mod. #4
HV=+-40V, Ibias=1,6µA
CO2 cooling on, Tin=-19,6°C, Tout=-21.3°C

I²C settings for cooled APV chips

e:\cvi-projects\apvdaq_fadc\origami6_V2_multi6_cooled.cfg

SMU:  +HV=Inv.Nr. 545-77    -HV=Inv.Nr. 540-702

HVret configuration:

0 ... switch open / not connected
1 ... switch closed / connected
 

SMU Dock Box J5 J6 J7
0 0 (now isolated) 1 1 0

J7... HV ret @ hybrid

same configuration as run112 but now the step motors of the xz table are powered.

Attachment 1: run112-113.jpg  79 kB  Uploaded Wed Mar 7 17:04:14 2012  | Hide | Hide all
run112-113.jpg
ELOG V3.1.5-fc6679b