Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-rd50-desy-Oct2024 testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS October 2011  Not logged in ELOG logo
Message ID: 83     Entry time: Wed Feb 22 18:32:24 2012
Author: Christian Irmler 
Project: BELLE 
Subject: Origami Module #4 
Run Number: run107 
Events: 50k 
StartTime: 22.02.2012 18:30:33 
EndTime: 22.02.2012 18:40:11 
Data: Good 

Sr90, large scintillator,
Origami Mod. #4
HV=+-40V, Ibias=1,6µA
CO2 cooling on, Tin=-20.5°C, Tout=-21.5°C

I²C settings for cooled APV chips --> same as used in run010

e:\cvi-projects\apvdaq_fadc\origami6_V2_multi6_cooled.cfg

Lab measurement with new dark box but old, large scintillator

SMU:  +HV=Inv.Nr. 545-77    -HV=Inv.Nr. 540-702

HVret configuration:

0 ... switch open / not connected
1 ... switch closed / connected
 

SMU Dock Box J5 J6 J7
0 1 0 0 1

J7... HV ret @ hybrid

Same as run106, but now J7 closed

APV pedestals slightly unstable.

Attachment 1: run107_apv5_raw_data.jpg  536 kB  | Hide | Hide all
run107_apv5_raw_data.jpg
Attachment 2: run107.jpg  86 kB  | Hide | Hide all
run107.jpg
ELOG V3.1.5-fc6679b