Message ID: 26     Entry time: Tue Oct 4 10:44:48 2011
Author: Christian Irmler 
Project: Micron 
Subject: Internal Calibration 
Run Number: cal003 
Events: 83800 
StartTime: 04.10.2011 10:33:50 
EndTime: 04.10.2011 10:48:51 
Data:  

micronbaby p-spray/irrad
HV = -100V
beam on, baseline of irrad APV reduced

APV #2 (I²C addr. 40) deactivated, latency error after initialization, reset line open?