  HEPHY logbook for testbeam at SPS September/October 2010  Not logged in ELOG logo
Message ID: 93     Entry time: Wed Oct 6 16:33:55 2010
Author: Markus Friedl 
Project: Micron Baby 
Subject: run 
Run Number: run051 
Events: 90000 
StartTime: 06.10.2010 16:32:03 
EndTime: 06.10.2010 20:59:58 

8 x Micron Baby (3 irradiated), no cooling
HV=100V I=209uA (start of run, still rising); 203uA (end of run)
beam on, NIM trigger from TLU (no handshake)
telescope position 131 / 53.5 / 7.5
 

no telescope run - being tuned (some intervals during data taking are possible)

 