Message ID: 7
Entry time: Thu Sep 23 16:01:10 2010
|
Author: |
Manfred Valentan |
Project: |
Micron Baby |
Subject: |
Modul B2Micron_2826_7_Baby3 -> DUT |
Run Number: |
|
Events: |
|
StartTime: |
|
EndTime: |
|
|
|
p-side: Hybrid 40
APV3: letzte 10 Streifennicht gebondet, ging sich beim Prototyp-Modul an der Stelle nicht aus
n-side: Hybrid 30
APV5: 57-64 schlecht, rebond fail?
ALS DUT GEEIGNET!
|
|
|
|
|
|
|
|
|
|
|
|