Message ID: 32     Entry time: Wed Sep 29 11:09:10 2010
Author: Markus Friedl 
Project: BELLE 
Subject: run 
Run Number: run010 
Events: 30000 
StartTime: 29.09.2010 11:08:03 
EndTime: 29.09.2010 11:50:07 

zero suppressed (HIT5) @ FADC

Belle stack: Origami-Micron-Micron-Origami - HIT5
HV=100V, Ibias=28A, beam on
cooling: Origami only, chiller: -25C, Module: -10C
modified I2C settings for cooled modules
centered in both axes

telescope run 20085