Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-rd50-desy-Oct2024 testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS September/October 2010  Not logged in ELOG logo
Message ID: 30     Entry time: Wed Sep 29 09:39:33 2010
Author: Markus Friedl 
Project: BELLE 
Subject: cal 
Run Number: cal003 
Events: 83800 
StartTime: 29.09.2010 09:38:00 
EndTime:  

same as cal002, but now with corrected readout order

ELOG V3.1.5-fc6679b