Message ID: 19     Entry time: Tue Sep 28 12:54:33 2010
Author: Markus Friedl 
Project: BELLE 
Subject: run 
Run Number: run002 
Events:  
StartTime: 28.09.2010 12:46:54 
EndTime:  

same as run001 after shifting x by 48mm

103 / 30 / 277.5 ? unsure after crash of xy stage PC