Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS June 2009  Not logged in ELOG logo
Message ID: 96     Entry time: Tue Aug 25 09:53:16 2009
Author: Marko Dragicevic 
Project: Pt_ITE512 
Subject: Pt_ITE512 4deg NO air! 
Run Number: run035 
Events: 20k 
StartTime: 25.08.2009 09:50 
EndTime: 25.08.2009 11:00 

Pt: 4 Grad, HV=200V, 0% (start run) to 14% (end run) RH, beam on, 120GeV

ITE512: HV=70V,
X-Y-Table: x=99.6, y=36
ELOG V3.1.5-fc6679b