Message ID: 96     Entry time: Tue Aug 25 09:53:16 2009
Author: Marko Dragicevic 
Project: Pt_ITE512 
Subject: Pt_ITE512 4deg NO air! 
Run Number: run035 
Events: 20k 
StartTime: 25.08.2009 09:50 
EndTime: 25.08.2009 11:00 

Pt: 4 Grad, HV=200V, 0% (start run) to 14% (end run) RH, beam on, 120GeV

ITE512: HV=70V,
X-Y-Table: x=99.6, y=36