Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-rd50-desy-Oct2024 testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS June 2008  Not logged in ELOG logo
Message ID: 22     Entry time: Sun Jun 1 08:06:57 2008
Author: stephan hänsel 
Project: SiLC 
Subject: APVDAQ + telescope (raw) 
Run Number: run2721-2737 
Events: 22000 
StartTime: 01.06.2008 - 08:01:53 
EndTime: 01.06.2008 - 14:19:13 
SiLC beam test - CERN SPS June 2008
8 modules, HV=100V, 40MHz, 6 samples, hor stage :=-7.5 mm
trigger: 9 mm opening, TLUControl.exe -d 10 -a 12
telescope: raw, new firmware

horizontal position ("target") = -7.5mm
this is LEFT position
ELOG V3.1.5-fc6679b