  MedAustron 2021, Page 3 of 18  Not logged in ELOG logo
Entry  Wed Jan 20 17:47:24 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 75, Ramon+Tracker, 800, , , 30 spills, , 12%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50,
setting VI

few outlier, fewer fluctuations
final setting VI
steering setting IV

Entry  Wed Jan 20 17:56:06 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 84, Ramon+Tracker, 800, , , 30 spills, , 12%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50,
setting VI steering VII,beam is off again

Entry  Wed Jan 20 17:42:02 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 68, Ramon+Tracker, 800, , , 30 spills, , 11%, 60%, 20, 10, 6dB, , ,  

MT=1, BSY=50,
setting IV
 

Entry  Wed Jan 20 17:42:31 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 69, Ramon+Tracker, 800, , , 30 spills, , 11%, 60.5%, 20, 10, 6dB, , ,  

MT=1, BSY=50,
setting IV
 

Entry  Wed Jan 20 17:42:38 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 71, Ramon+Tracker, 800, , , 30 spills, , 11%, 60.25%, 20, 10, 6dB, , ,  

MT=1, BSY=50,
setting IV
 

Entry  Wed Jan 20 17:46:32 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 74, Ramon+Tracker, 800, , , 30 spills, , 11%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50,
potential setting VI

few outlier, fewer fluctuations
steering setting IV

Entry  Wed Jan 20 17:44:19 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 73, Ramon+Tracker, 800, , , 30 spills, , 100%, 60.5%, 20, 10, 6dB, , ,  

MT=1, BSY=50,
setting V

spot still centered
quite stable
~120kHz
steering setting IV

Entry  Wed Jan 20 17:47:53 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 76, Ramon+Tracker, 800, , , 30 spills, , 100%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50,

beam off
potential setting VII
steering setting IV

Entry  Wed Jan 20 17:51:28 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 77, Ramon+Tracker, 800, , , 30 spills, , 100%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50,

beam off
potential setting VII
steering setting IV + 1cm in +y direction

Entry  Wed Jan 20 17:51:50 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 79, Ramon+Tracker, 800, , , 30 spills, , 100%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50

beam off
potential setting VII
steering setting IV + 1cm in +y direction

Entry  Wed Jan 20 17:52:12 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 80, Ramon+Tracker, 800, , , 30 spills, , 100%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50

beam off
potential setting VII
steering setting IV + shift in -y direction

Entry  Wed Jan 20 17:52:28 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 81, Ramon+Tracker, 800, , , 30 spills, , 100%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50,

beam off
potential setting VII
steering setting IV + bigger shift in -y direction

Entry  Wed Jan 20 17:52:49 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 82, Ramon+Tracker, 800, , , 30 spills, , 100%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50,
potential setting VII
new steering +12.5mm x,+10mm y ( -beam direction), still off

Entry  Wed Jan 20 17:55:13 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 83, Ramon+Tracker, 800, , , 30 spills, , 100%, 60.5%, 20, 30, 6dB, , ,  

MT=1, BSY=50,
final setting VII
new steering VII +12.5mm x,+13mm y ( -beam direction)

Entry  Wed Jan 20 17:57:16 2021, Felix Ulrich-Pur, Lowflux p800 commissioning, 85, Ramon+Tracker, 800, , , 30 spills, Unknown, 100%, 60.5%, 20, 10, 6dB, , ,  

MT=1, BSY=50,
setting V steering VII,beam looks centered, but rate and spot looks similar to setting VII, maybe wrong acc setting? --> don't use

Entry  Sun Jan 10 06:27:26 2021, Maximilian Tomaschek, Lowflux recommissioning, 1, Ramon+Tracker, 252.7, , , 30 spills, , 10%, , 10, 1, , , ,  

Rate,15s spill pause, delay can be set by operator

Entry  Sun Jan 10 06:32:13 2021, Maximilian Tomaschek, Lowflux recommissioning, 2, Ramon+Tracker, 194.3, , , 30 spills, , 10%, , 10, 1, , , ,  

Rate

Entry  Sun Jan 10 06:33:22 2021, Maximilian Tomaschek, Lowflux recommissioning, 3, Ramon+Tracker, 175.3, , , 30 spills, , 10%, , 10, 1, , , ,  

Rate

Entry  Sun Jan 10 06:33:44 2021, Maximilian Tomaschek, Lowflux recommissioning, 5, Ramon+Tracker, 100.4, , , 30 spills, , 10%, , 10, 1, , , ,  

Rate

Entry  Sun Jan 10 06:38:16 2021, Maximilian Tomaschek, Lowflux recommissioning, 6, Ramon+Tracker, 83, , , 30 spills, , 10%, , 10, 1, , , ,  

Rate