ID Date Author Project Subject Run Numberdown Events XYPosition Cooling Data
  20   Thu Apr 13 16:31:55 2017 Johannes GrossmannMaPSATeleskope Correlation910000000NoUnknown

Telescope 1237

  19   Thu Apr 13 16:23:35 2017 Johannes GrossmannMaPSATeleskope Correlation710000000NoUnknown

Telescope 1236

threshold 90 

 

  66   Fri Apr 14 13:21:07 2017 Johannes GrossmannMaPSAAlignment Check662500000NoUnknown

Telescope 1318

Threshold 100

Mapsa CLK Delay 0

Reference Plane Lost aber Anfang Gut

  64   Fri Apr 14 12:58:08 2017 Johannes GrossmannMaPSAAlignment Check642500000NoUnknown

Telescope 1316

Threshold 80

Mapsa CLK Delay 0

Reference Plane Lost aber Anfang Gut

  126   Tue Apr 18 21:55:44 2017 Johannes GrossmannMaPSARotation63500NoUnknown

HV 100 V Threshold 75 Winkel 15

16:14 17.4.2017

Telescope Runnumber 1887

  135   Thu Apr 20 10:07:30 2017 Johannes GrossmannMaPSARotation63500NoUnknown

HV 100 V Threshold 75 Winkel 25

16:14 17.4.2017

Telescope Runnumber 1887

  63   Fri Apr 14 12:48:44 2017 Johannes GrossmannMaPSAAlignment Check612500000NoUnknown

Telescope 1314

Threshold 80

Mapsa CLK Delay 0

Reference Plane Lost aber Anfang Gut

  120   Tue Apr 18 16:16:59 2017 Johannes GrossmannMaPSAStd Settings60400NoUnknown

Changed HV 100 V Threshold 75

16:14 17.4.2017

Telescope Runnumber 1855

  62   Fri Apr 14 12:26:00 2017 Johannes GrossmannMaPSAAlignment Check602500000NoUnknown

Telescope 1312

Threshold 80

Mapsa CLK Delay 0

Carbon fiber  broken at 2:20 AM. Alignement check.

  117   Mon Apr 17 23:52:47 2017 Johannes GrossmannMaPSAHV_Scan52300NoUnknown

Changed HV 80 V

23:50 17.4.2017

  116   Mon Apr 17 23:50:59 2017 Johannes GrossmannMaPSAHV_Scan52200NoUnknown

Changed HV from 90 V to 80 V

Kann ich wegwerfen!

23:49 17.4.2017

  58   Fri Apr 14 01:33:35 2017 Johannes GrossmannMaPSATeleskope Correlation522500000NoUnknown

Telescope 1296

Threshold 90 

Mapsa CLK Delay 0 

  57   Fri Apr 14 00:40:23 2017 Johannes GrossmannMaPSATeleskope Correlation51500000NoUnknown

Telescope 1294

Threshold 90 

Mapsa CLK Delay 24 ns

  56   Fri Apr 14 00:22:30 2017 Johannes GrossmannMaPSATeleskope Correlation50500000NoUnknown

Telescope 1292

Threshold 90 

Mapsa CLK Delay 22 ns

  55   Fri Apr 14 00:12:53 2017 Johannes GrossmannMaPSATeleskope Correlation49500000NoUnknown

Telescope 1292

Threshold 90 

Mapsa CLK Delay 20 ns

  110   Mon Apr 17 17:55:55 2017 Johannes GrossmannMaPSAHV_Scan48800NoUnknown

Changed HV from 120 V to 90 V

17:53 17.4.2017

  53   Fri Apr 14 00:01:03 2017 Johannes GrossmannMaPSATeleskope Correlation48500000NoUnknown

Telescope 1288

Threshold 90 

Mapsa CLK Delay 18 ns

  54   Fri Apr 14 00:12:05 2017 Johannes GrossmannMaPSATeleskope Correlation48500000NoUnknown

Telescope 1288

Threshold 90 

Mapsa CLK Delay 20 ns

  52   Thu Apr 13 23:50:36 2017 Johannes GrossmannMaPSATeleskope Correlation47500000NoUnknown

Telescope 1286

Threshold 90 

Mapsa CLK Delay 16 ns

  51   Thu Apr 13 23:40:26 2017 Johannes GrossmannMaPSATeleskope Correlation46500000NoUnknown

Telescope 1284

Threshold 90 

Mapsa CLK Delay 14 ns