Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  Alibava/Mapsa testbeam at DESY in April 2017 (Axel, Grossi)  Not logged in ELOG logo
Message ID: 131     Entry time: Wed Apr 19 22:56:07 2017
Author: Axel Koenig 
Project: ALiBaVa (IFX) 
Subject: run_005_Irrad_450V.dat 
Run Number: 005 
Events: 2800000 
XYPosition: 96, 64, 360 
Cooling: No 
Data: Unknown 

Remarks: Telescope run 635. Bias scan -450V, central position of sensor (DUT parallel to telescope planes at 360 deg due to different fixation compared to other DUTs). Telescope geometry identical to double irrad module.

Backside Biasing! Run crashed over night. Triggers valid up to 2032867.

Telescope chiller turned on (15 deg).

Parameter Value
Alibava run run_005_Irrad_450V.dat
Telescope run 635
Triggers 2800000
Alibava trigger eff. ~70%
Beam energy 5.6 GeV
Telescope threshold 6
Bias voltage -450
Latency 132
Table x 96 mm
Table z 64 mm
Tabe rot

360 deg

Temperature at DUT -14.5 +- 1 deg. celsius
Current 38.8 uA
ELOG V3.1.5-fc6679b