Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-rd50-desy-Oct2024 testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  Silicon Envelope for the Large Protoype TPC  Not logged in ELOG logo
Message ID: 29     Entry time: Fri Nov 27 12:21:00 2009
Author: Stephan Hänsel 
Type: Measurements 
Subject: Run 20074 - Micromegas 816 

10010 events

with 2 Micromegas modules (TPCDAQ stopped at 10003 events)

Beam: 5,6 GeV

silicon sledge 35cm inside from TPC-support-front and 36mm above center position

  • -> front Z: 5mm too far inside the gap
  • -> back Z: 5mm too far outside the gap

rate: 4,1 Hz

HV: 200V -> 1,2µA

LV:

  • 01,30 / 02,60   //   01.30 / 02.60
  • 0,632 / 1,739   //   0,622 / 1,752

 

 

 

Attachment 1: OneTrackEvents_020074.txt  15 kB  Uploaded Mon Jan 11 15:56:48 2010  | Show | Show all
Attachment 2: TwoTrackEvents_020074.txt  268 Bytes  Uploaded Mon Jan 11 15:56:59 2010  | Show | Show all
ELOG V3.1.5-fc6679b