Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-RD50-DESY-Apr2024 testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  Belle testbeam at SPS in June 2015  Not logged in ELOG logo
Message ID: 1     Entry time: Tue May 12 10:27:39 2015
Author: Benedikt Würkner 
Project: SVD3 (H6B) 
Subject: Setup information 
Run Number:  
Events:  
XYPosition:  
Cooling:  
Data: Unknown 

Information concerning the SVD3 setup during a beam test

In the beam area setup the whole crate and the power supply with the usual spider cable and the two Keithly 2410 high voltage supplies. Monitoring of the 2410 happens via a NI MAX interface that connects to the GPIB-Ethernet interface and needs to be configured there. The IP and password are noted on the device. The software can be found on heros in medialib/LONGTERM/longterm R3.1_doubleSided as a normal *.vi file. 

Default adresses 16 and 17 as defined in labview, need to figure out on site which is which, if the voltage selected (e.g. 100V) is applied as +50/-50 or if it is applied as +100/-100 before connecting the cables. 

Take a run without dut as well to check the telescope integrity. Without dut in beamline!!!!!

Attachment 1: spider-config.jpg  690 kB  Uploaded Mon May 18 15:23:01 2015  | Hide | Hide all
spider-config.jpg
ELOG V3.1.5-fc6679b