Home CMS Production Clean room MedAustron HEPHY testbeams old
testbeam-RD50-DESY-Jul2023 testbeam-RD50-CERN-Oct2022 testbeam-DESY-Oct2017 testbeam-DESY-April2017 testbeam-SPS2015 testbeam-SPS2014 testbeam-DESY14 testbeam-SPS12 testbeam-SPS11 testbeam-SPS10 testbeam-SPS09 testbeam-SPS08 LP-TPC
  HEPHY logbook for testbeam at SPS June 2009, Page 1 of 6  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Project Subject Run Number Eventsup StartTime EndTime Text Attachments
  1   Mon Jul 6 12:22:47 2009 Stephan HänselSiLCMeasurements - hybrids with APV    Pt Modules: 
Hybrids with 4 APVs:
  
 
  
  2   Mon Jul 6 12:24:53 2009 Stephan HänselSiLCModule Drawings     Pt Modules: 

    
3D-View 
    technical drawings:
  
  5   Mon Jul 6 12:29:20 2009 Stephan HänselSiLCSensors - layout     Pt Modules: 
CMS OB1 Sensors:

    
 Wafer-Screenshot.png 
  6   Mon Jul 6 14:30:45 2009 Marko Dragicevic Equipment List    [B]Slow Control:[/B]
Source Measurement Unit Keithley K2410, Inv.Nr.:
540-702, 2000EUR
 carnet_aug09.xls 
  7   Mon Jul 6 16:22:36 2009 Stephan HänselSiLCMeasurements - Sensors     Pt Modules: 
OB1-Sensors:
     30210331516116
  
  8   Mon Jul 6 16:23:51 2009 Stephan HänselSiLCModule Components     Pt Modules: 

Pt-1:
  
  9   Thu Jul 9 10:29:58 2009 Stephan HänselSiLCMeasurements - Modules     Pt Modules:

- Sensoren sind Luftfeuhtigkeitsempfindlich
  
  10   Fri Jul 17 14:03:21 2009 Stephan Hänsel What to measure     Origami
 
Testbeam08 Module
  
  11   Fri Jul 31 19:23:26 2009 Thomas Bergauer Laser Spot size    10cm nach Kollimator: Durchmesser 1.45mm (FWHM)
20cm
nach Kollimator: Durchmesser 1,54mm (FWHM)
 laser_spot_overview.jpglaser_spot_10cm.jpglaser_spot_20cm.jpglaser_spot_30cm.jpg 
  12   Tue Aug 11 14:03:57 2009 Marko Dragicevic Sensor Designs    Screenshots
HEPHY
Gallery
GDS File Viewer
 
 6x 
  13   Fri Aug 14 16:45:25 2009 Stephan Hänsel Module - Setups     

    5mm Inbus-Schlüssel

   3mm Inbus Schlüssel
  
  
  14   Fri Aug 14 19:35:43 2009 Thomas BergauerPt_ITE512intcal    HV=100V except h05-ITE-512 and h06-ITE-512
(runaway, HV off)
h01-Pt: 10uA
  
  15   Fri Aug 14 21:36:17 2009 Markus Friedl Config files    Status of config files as of Friday 14
August 2009 late evening
  
  16   Wed Aug 19 15:37:37 2009 Christian IrmlerITE128internal calibrationcal001 15:31:29 8 modules, HV=70V, 40MHz, 1 sample
no beam 
APV 4,5: inverter off, higher baseline
  
  17   Wed Aug 19 15:41:17 2009 Wolfgang KiesenhoferSiLCangle scan templates    Linie am rechten Seitenrand (in der Vorschau
unten leider nicht gut zu sehen) sollte mit
dem rechten Rand der Basisplatte abschließen
 13x 
  20   Wed Aug 19 22:57:13 2009 Marko Dragicevic How-To    TLU (run from DAQPCHEPHY):
ssh
eudet@eudetmac001.cern.ch
ssh tlupc
  
  21   Thu Aug 20 00:16:45 2009 Christian IrmlerITE128pedestal correctionpedcorr001 20.08.2009 00:14:2120.08.2009 00:24:28DUT: SiLC 08_1, 6 x ITE128, SiLC 08_2
HV = 70V, 40MHz
pedestal correction
  
  23   Thu Aug 20 10:48:39 2009 Christian Irmleralignment_beaminternal calibrationcal002 20.08.2009 10:49:0720.08.2009 10:59:432 alignement modules
location in beam direction: h04-h03
HV=70V, 40MHz, 1 sample
  
  24   Thu Aug 20 11:05:26 2009 Christian Irmleralignment_beampedeatal correctionpedcorr002 20.08.2009 11:05:4120.08.2009 11:09:352 alignement modules
location in beam direction: h04-h03
HV=70V, 40MHz, 1 sample
  
  32   Thu Aug 20 15:50:58 2009 Manfred Valentanalignment_laserslow control: HV graphall alignemnt_laser runs 20.08.09 10:364h 43m 52s laterblue graph: h03
white graph: h04
 slow_control_alignment_sensors.gif 
ELOG V3.1.5-fc6679b