ID Date Author Projectup Subject Run Number Events StartTime EndTime Text Attachments
  1   Tue May 6 13:51:43 2008 Thomas BergauerotherEquipment list    [B]Slow Control:[/B]
K2410 SMU
K2700 Scanning Voltmeter
  
  8   Mon May 19 15:14:40 2008 Markus FriedlotherTentative Beam Test Schedule    Wed 28 May: ~16:00 arrival, unpacking
Thu 29 May: installation
Fri 30 May: beam on
  
  9   Mon May 19 15:21:49 2008 Markus FriedlotherCERN SPS page 1    SPS Status
SPS
Page 1 - http://hpslweb.cern.ch/frame/java/1.1/view110-java.html
  
  12   Fri May 30 10:36:18 2008 Marko DragicevicotherImportant Information/Contact    [B]IPs[/B]
Linksys Router
[LIST]
  
  19   Sat May 31 18:33:50 2008 Thomas Bergauerotherbeam profile    [SIZE=3][B]Beam configuration[/B][/SIZE]
Beam configuration file: H6b.802 (FM HAD
(P0 off, H8=+180) PARLALLEL IN H6B SILC 2008
 Picture_1.pngbeamline_settings.png 