Message ID: 28     Entry time: Thu Nov 5 19:46:15 2009
Author: Stephan Hänsel 
Type: Measurements 
Subject: Run 20073 - Micromegas 815 

10070 events

with 2 Micromegas modules (TPCDAQ stopped at 9864 events)

Beam: 5,6 GeV

silicon sledge 35cm inside from TPC-support-front and 36mm above center position

  • -> front Z: 5mm too far inside the gap
  • -> back Z: 5mm too far outside the gap

 

HV: 200V -> 1,2µA

LV:

  • 01,30 / 02,60   //   01.30 / 02.60
  • 0,632 / 1,739   //   0,622 / 1,752

 

 

 

Attachment 1: OneTrackEvents_020073.txt  15 kB  Uploaded Mon Jan 11 15:55:36 2010  | Show | Show all
Attachment 2: TwoTrackEvents_020073.txt  261 Bytes  Uploaded Mon Jan 11 15:55:53 2010  | Show | Show all